Power Decision Lab.
Price a day of electricity, then test how much IT load a utility connection can support. Change the assumptions and follow the numbers back to the meter.
01 / Contract comparison
What does the buyer pay?
One site, one UTC day, three ways to pay for the same 496 MWh. All prices and contract terms are illustrative.
Market scenario
The facility buys at the load-zone price. The PPA settles at the generator node, including a negative price at noon.
Virtual PPA + utility has the lowest modeled cost today, $207 below the next option.
Receipt subtracted from the utility bill.
Generator-node price weighted by MWh generated.
179 of 496 MWh overlaps; surplus cannot cover a later hour.
Contract assumptions and settlement formulas
Utility only. Sum hourly load × (load-zone price + $12/MWh delivery). This simplified comparator excludes demand charges and taxes.
Virtual power purchase agreement (PPA). Keep the site bill and subtract the buyer’s settlement: Σ generation × (generator-node price − strike). The plant sells into its own market. Negative settlement is a buyer payment.
Energy services agreement (ESA). Here the provider supplies all metered load for the bundled rate plus $300/day. This replaces the modeled utility bill. Actual agreements can treat pass-through charges, minimum takes and escalation differently.
Scope. One day, one grid, no storage dispatch. The solar overlap assumes eligible attributes dedicated to this load. It excludes residual grid supply and is neither a verified carbon-free energy score nor an emissions claim. A deal decision also needs a longer price, load and tariff history.
Reference: U.S. EPA on financial PPAs ↗02 / Capacity screen
What can the site promise?
A separate design-hour example. A tenant requests 20 MW of IT load. Test it against firm service at each utility milestone.
Utility milestone
The ratio already includes cooling and auxiliary power. Reserve is deducted once, on the facility side.
at this milestone
Meets the 20 MW request exactly; there is no extra IT headroom.
Capacity formula and limits
IT MW = max(0, firm facility MW − facility reserve MW) ÷ design-hour facility-to-IT ratio. At the default expansion milestone: (30 − 3) ÷ 1.35 = 20 MW. The ratio is a planning assumption, not annual measured PUE. No credit is given to intermittent solar, uncontracted bridge power or battery nameplate. Firm service, redundancy, cooling performance and storage duration need independent checks before a commitment.
03 / Reproduce the analysis
From a meter row to a bill.
Use the same CSV, Python runner and SQLite transformation behind this page. The sample runs locally with the Python standard library.
Data quality / Base day
98 raw readings → 24 hours
- Normalize energy units. At 05:00, 18,000 kWh becomes 18 MWh.
- Resolve revisions. Ignore one repeated 04:00 meter reading. The revised noon solar reading, 30 MWh, replaces 32 MWh.
- Preserve missing prices. 24/24 generator-node prices available. A missing price at an active generation hour blocks the PPA total; a negative price remains valid.
python replay.py --case base --strike 48 --esa 80of the day’s load overlaps solar output in the same hour.
Inspect all 24 hourly records · Base day
| UTC | Load (MWh) | Solar (MWh) | Load zone ($/MWh) | Gen. node ($/MWh) |
|---|---|---|---|---|
| 00:00 | 17 | 0 | 54 | 48 |
| 01:00 | 16 | 0 | 50 | 46 |
| 02:00 | 16 | 0 | 48 | 45 |
| 03:00 | 16 | 0 | 49 | 46 |
| 04:00 | 17 | 0 | 51 | 50 |
| 05:00 | 18 | 0 | 58 | 58 |
| 06:00 | 19 | 1 | 65 | 69 |
| 07:00 | 20 | 4 | 72 | 77 |
| 08:00 | 21 | 9 | 71 | 75 |
| 09:00 | 22 | 15 | 65 | 70 |
| 10:00 | 23 | 21 | 60 | 60 |
| 11:00 | 23 | 26 | 58 | 51 |
| 12:00 | 24 | 30 | 56 | -5 |
| 13:00 | 24 | 28 | 59 | 45 |
| 14:00 | 23 | 24 | 62 | 55 |
| 15:00 | 22 | 18 | 69 | 65 |
| 16:00 | 23 | 11 | 76 | 72 |
| 17:00 | 24 | 5 | 91 | 85 |
| 18:00 | 25 | 1 | 107 | 91 |
| 19:00 | 24 | 0 | 103 | 90 |
| 20:00 | 22 | 0 | 91 | 78 |
| 21:00 | 20 | 0 | 78 | 70 |
| 22:00 | 19 | 0 | 67 | 63 |
| 23:00 | 18 | 0 | 58 | 52 |
Start with the decision
What would change the decision at your site?
A load trace, a draft term sheet, and a target power-on date are useful starting points. We can identify which assumptions need to be tested first.