HelioVector / Applied energy analytics

Power Decision Lab.

Price a day of electricity, then test how much IT load a utility connection can support. Change the assumptions and follow the numbers back to the meter.

01 / Contract comparison

What does the buyer pay?

One site, one UTC day, three ways to pay for the same 496 MWh. All prices and contract terms are illustrative.

Market scenario

The facility buys at the load-zone price. The PPA settles at the generator node, including a negative price at noon.

$48/MWh
$80/MWh
Buyer’s ledgerUSD / modeled day
Site tariffUtility only
$40,105
Financial hedgeVirtual PPA + utility
$39,773
Bundled serviceIllustrative ESA
$39,980

Virtual PPA + utility has the lowest modeled cost today, $207 below the next option.

Buyer PPA settlement$332

Receipt subtracted from the utility bill.

Generation capture price$49.72

Generator-node price weighted by MWh generated.

Same-hour solar overlap36.1%

179 of 496 MWh overlaps; surplus cannot cover a later hour.

Contract assumptions and settlement formulas

Utility only. Sum hourly load × (load-zone price + $12/MWh delivery). This simplified comparator excludes demand charges and taxes.

Virtual power purchase agreement (PPA). Keep the site bill and subtract the buyer’s settlement: Σ generation × (generator-node price − strike). The plant sells into its own market. Negative settlement is a buyer payment.

Energy services agreement (ESA). Here the provider supplies all metered load for the bundled rate plus $300/day. This replaces the modeled utility bill. Actual agreements can treat pass-through charges, minimum takes and escalation differently.

Scope. One day, one grid, no storage dispatch. The solar overlap assumes eligible attributes dedicated to this load. It excludes residual grid supply and is neither a verified carbon-free energy score nor an emissions claim. A deal decision also needs a longer price, load and tariff history.

Reference: U.S. EPA on financial PPAs ↗

02 / Capacity screen

What can the site promise?

A separate design-hour example. A tenant requests 20 MW of IT load. Test it against firm service at each utility milestone.

Utility milestone

3.0 MW
1.35×

The ratio already includes cooling and auxiliary power. Reserve is deducted once, on the facility side.

Facility → ITDesign hour · MW
20.0MW of IT load
at this milestone
IT load20.0 MW
Cooling & auxiliaries7.0 MW
Facility reserve3.0 MW

Meets the 20 MW request exactly; there is no extra IT headroom.

Capacity formula and limits

IT MW = max(0, firm facility MW − facility reserve MW) ÷ design-hour facility-to-IT ratio. At the default expansion milestone: (30 − 3) ÷ 1.35 = 20 MW. The ratio is a planning assumption, not annual measured PUE. No credit is given to intermittent solar, uncontracted bridge power or battery nameplate. Firm service, redundancy, cooling performance and storage duration need independent checks before a commitment.

03 / Reproduce the analysis

From a meter row to a bill.

Use the same CSV, Python runner and SQLite transformation behind this page. The sample runs locally with the Python standard library.

Data quality / Base day

98 raw readings → 24 hours

  1. Normalize energy units. At 05:00, 18,000 kWh becomes 18 MWh.
  2. Resolve revisions. Ignore one repeated 04:00 meter reading. The revised noon solar reading, 30 MWh, replaces 32 MWh.
  3. Preserve missing prices. 24/24 generator-node prices available. A missing price at an active generation hour blocks the PPA total; a negative price remains valid.
Download the model (.zip) python replay.py --case base --strike 48 --esa 80
Fieldnotes / Fig. 0124 hours · UTC
When solar meets the loadOne illustrative day at a data center meter.
Hourly site load and solar generationLoad continues overnight. Solar peaks at 30 MWh at noon. Only 179 of 496 MWh of site load overlaps solar in the same hour.010203000:0006:0012:0018:0023:00MWh
Site loadSolar outputHourly overlap
36.1%

of the day’s load overlaps solar output in the same hour.

Synthetic data HV / POWER STUDIES
Inspect all 24 hourly records · Base day
June 21, 2026 · synthetic hourly inputs · interval start, UTC
UTCLoad (MWh)Solar (MWh)Load zone ($/MWh)Gen. node ($/MWh)
00:001705448
01:001605046
02:001604845
03:001604946
04:001705150
05:001805858
06:001916569
07:002047277
08:002197175
09:0022156570
10:0023216060
11:0023265851
12:00243056-5
13:0024285945
14:0023246255
15:0022186965
16:0023117672
17:002459185
18:0025110791
19:0024010390
20:002209178
21:002007870
22:001906763
23:001805852

Start with the decision

What would change the decision at your site?

01 / Your asset02 / Your decision03 / Your timeline

A load trace, a draft term sheet, and a target power-on date are useful starting points. We can identify which assumptions need to be tested first.

ray@heliovector.ai New Jersey / New York · Working across North America